Schedule & Progress
Progress throughout March 2010:
Landscaping on courtyard 1 & 2 completed
North landscaping has started
Oxygen trench at the entrance ongoing
Fire stopping to all lifts complete
CCTV cabling ongoing
Start of soft floor in stair case
Progress of internal trades snagging has reached 50%
South canopy glass installation complete, except for 4 glass panels that were manufactured incorrectly
Progress throughout February 2010:
Final connections on drainage
Waterproofing under Helipad ongoing
Completion of Breast Care Unti
Snagging works ongoing
Holt & cold water supplies are now in all kitchens
Core 3 lifts installed
East link bridge glass cladding, completed
Progress throughout January 2010:
Courtyard 4 landscaping started
Main building finishes ongoing
Door frames ongoing on all levels
Cubicle tracks ongoing on all levels
Painting 1st coat, complete
Door installation, ongoing
FF&E installation ongoing
Blinds, wall protection, access panels ongoing
Progress throughout December 2009:
Landscaping in courtyard 1 substantially complete
Waterproofing under Helipad complete
Demolition of atrium facade complete
Risers are completed and fireproofed
Core 2 lift tested and now in use
Helipad containment complete
Progress throughout November 2009:
Waterproofing work are complete
SCP surface concrete ongoing
Generator room completed
TC5 dismantled
Painting 2nd coat on L1 - 3
First fix for medical equipment
Progress throughout October 2009:
TC5 ready for dismantling
Helipad finishing works ongoing
Flues to boiler rooms ongoing
External mains complete
Generators installation ongoing
Audiology booth ongoing
Dry lining complete
Progress throughout September 2009:
South car park structure completed
Helipad, ongoing
Electrical works to South Car Park have commenced
Balustrades in stair cases starting
Aluminium cladding in courtyard 2 completed
Partitions 1st fix completion
Installation on IT cabling, ongoing
Progress throughout August 2009:
TC4 dismantaled
Installation on IT cabling, ongoing
Window frame installation @ L5, completed
Render to courtyard 4 & 5, completed
Painting on L1-L3, ongoing
EDF power on to the site, installed
Progress throughout July 2009:
Helipad ramps and metal deck completed
Main building concrete finished, ongoing
M&E fix, Level 1 ongoing in all areas, progressing well
First fix for medical equipment started
Soft floor started in L1
Atrium infill roofs completed
Ceiling grids in L1 & L2 ongoing
Progress throughout June 2009:
Block work, ongoing
TC3 dismantling
Main building finishes, ongoing
M&E riser installation commenced
Door frames started in Level 1
Ceiling grids started in Level 1
Start of aluminium panels installation in courtyard 1
Progress throughout May 2009:
Main entrance back filling, complete
TC2 dismantled
Medical gases, 2st fix works continuing to Level 3 zones 1 to 4
Start of painting on Level 1
Window frames instalation completed to Level 4
Erection of the main entrance steel structure substantially complete
Helipad steelwork main structure complete and ramps started
Progress throughout April 2009:
L6 slab completed
Generator room completed
TC1 dismantled and re-erected as TC5
South car park foundations ongoing
Installation of IT cabling commenced at Level 1
L2 corridor partition first fix completed
Window frame installation @ Level 5 started
Progress throughout March 2009:
L6 slab started
Level 4 Plant room completion
Blockwork starting
Start of roof waterproofing
Rainwater connections at roof level ongoing in North section
L3 corridor partitioning first fix started
Window frame installation nearly completed @ Level 3
Progress throughout February 2009:
- L4 walls and columns completed
- L4 plant room in progress
- L5 walls and columns started
- Delivery and storage tanks completed
- L2 corridor partition first fix, in progress
- Render to site mock up, completed
- Start of west link bridge steelwork erection
Progress throughout January 2009:
- L3 walls and columns
- Level 5 beams and slab started
- Glass wall demolition completed
- Level 4 plant room started
- M&E first fix and drainage complete in Zone 1
- L2 head tracks installation completed
- Start of window frames in L3
Progress throughout December 2008:
- L4 walls started in L4
- L2 head tracks installation, 95% complete
- M&E drainage works continuing in Undercroft
- M&E 1st fix, ongoing at L1. Works commenced on L2, Zone 1
- Window frames installation nearly completed in L1
- Start of window frames in L2
Progress throughout November 2008:
- L3 slab completed
- L3 walls in progress
- L4 slabs and beams in progress
- M&E 1st fix in progress at L1
- Temporary waterproofing at L3
Progress throughout October 2008:
- L2 slab, complete
- L3 slabs completed in TC4
- L3 walla and beams in progress
- L4 beams and slabs started in TC4
- Electrical cast-in conduits ongoing in cores
- L1 head tracks installation ongoing
- M&E started at L1
- First delivery of window frames
Progress throughout September 2008:
- Drainage connection to the South loop road, completed
- L1 slab hollowcore planks and topping completed
- L2 slab hollowcore planks completed
- Undercroft waterproofing, ongoing
Progress throughout August 2008:
- L2 slabs concreting in TC4 area, ongoing
- L2 slabs concreting in TC1 area, started
- L2 walls started in Tc4 area
- Excavation for generator plant room completed and foundation raft concreting started
Progress throughout July 2008:
- Drainage diversions and connections of excisting under Main building substantially completed
- L1 slab hollowcore planks and topping at final stage
- L2 slabs concreting in TC4 area, started
- L2 beams installation in TC1 area, started
- Undercroft waterproofing, in progress
- Electrical csat-in conduits ongoing
- Workers facilities extension completed
- Planning discussions with CBC Planning Officer for Holding Area extension
Progress throughout June 2008:
- Drainage connection to the South loop road in progress
- Main building South drainage, completed
- Lightning protection installation and testing works ongoing
- Undercroft walls and L1 beams, final stage
- Undercroft circulation path, final stage
- L1 columns start
- Ceiling grid start
- Exemplar rooms partitioning, completed
- Exemplar rooms M&E first fix, completed
Progress throughout May 2008:
- Drainage works in the SUDS area in progress
- Erection of TC2
- Undercroft walls and L1 beams, ongoing
- L1 slab and hollowcore planks and topping, started
- Exemplar rooms partitioning, started
- Start of atrium facade alteration