Schedule & Progress

Progress throughout March 2010:

  • Landscaping on courtyard 1 & 2 completed
  • North landscaping has started
  • Oxygen trench at the entrance ongoing
  • Fire stopping to all lifts complete
  • CCTV cabling ongoing
  • Start of soft floor in stair case
  • Progress of internal trades snagging has reached 50%
  • South canopy glass installation complete, except for 4 glass panels that were manufactured incorrectly
  • Progress throughout February 2010:

  • Final connections on drainage
  • Waterproofing under Helipad ongoing
  • Completion of Breast Care Unti
  • Snagging works ongoing
  • Holt & cold water supplies are now in all kitchens
  • Core 3 lifts installed
  • East link bridge glass cladding, completed 
  • Progress throughout January 2010:

  • Courtyard 4 landscaping started
  • Main building finishes ongoing
  • Door frames ongoing on all levels
  • Cubicle tracks ongoing on all levels
  • Painting 1st coat, complete
  • Door installation, ongoing
  • FF&E installation ongoing
  • Blinds, wall protection, access panels ongoing
  • Progress throughout December 2009:

  • Landscaping in courtyard 1 substantially complete
  • Waterproofing under Helipad complete
  • Demolition of atrium facade complete
  • Risers are completed and fireproofed
  • Core 2 lift tested and now in use
  • Helipad containment complete
  • Progress throughout November 2009:

  • Waterproofing work are complete
  • SCP surface concrete ongoing
  • Generator room completed
  • TC5 dismantled
  • Painting 2nd coat on L1 - 3
  • First fix for medical equipment
  • Progress throughout October 2009:

  • TC5 ready for dismantling
  • Helipad finishing works ongoing
  • Flues to boiler rooms ongoing
  • External mains complete
  • Generators installation ongoing
  • Audiology booth ongoing
  • Dry lining complete
  • Progress throughout September 2009:

  • South car park structure completed
  • Helipad, ongoing
  • Electrical works to South Car Park have commenced
  • Balustrades in stair cases starting
  • Aluminium cladding in courtyard 2 completed
  • Partitions 1st fix completion
  • Installation on IT cabling, ongoing
  • Progress throughout August 2009:

  • TC4 dismantaled
  • Installation on IT cabling, ongoing
  • Window frame installation @ L5, completed
  • Render to courtyard 4 & 5, completed
  • Painting on L1-L3, ongoing
  • EDF power on to the site, installed

     

  • Progress throughout July 2009:

  • Helipad ramps and metal deck completed
  • Main building concrete finished, ongoing
  • M&E fix, Level 1 ongoing in all areas, progressing well
  • First fix for medical equipment started
  • Soft floor started in L1
  • Atrium infill roofs completed
  • Ceiling grids in L1 & L2 ongoing 
  • Progress throughout June 2009:

  • Block work, ongoing
  • TC3 dismantling
  • Main building finishes, ongoing
  • M&E riser installation commenced
  • Door frames started in Level 1
  • Ceiling grids started in Level 1
  • Start of aluminium panels installation in courtyard 1
  • Progress throughout May 2009:

  • Main entrance back filling, complete
  • TC2 dismantled
  • Medical gases, 2st fix works continuing to Level 3 zones 1 to 4
  • Start of painting on Level 1
  • Window frames instalation completed to Level 4
  • Erection of the main entrance steel structure substantially complete 
  • Helipad steelwork main structure complete and ramps started
  • Progress throughout April 2009:

  • L6 slab completed
  • Generator room completed
  • TC1  dismantled and re-erected as TC5
  • South car park foundations ongoing
  • Installation of IT cabling commenced at Level 1
  • L2 corridor partition first fix completed 
  • Window frame installation @ Level 5 started
  • Progress throughout March 2009:

  • L6 slab started
  • Level 4 Plant room completion
  • Blockwork starting
  • Start of roof waterproofing
  • Rainwater connections at roof level ongoing in North section
  • L3 corridor partitioning first fix started
  • Window frame installation nearly completed @ Level 3
  • Progress throughout February 2009:

    • L4 walls and columns completed
    • L4 plant room in progress
    • L5 walls and columns started
    • Delivery and storage tanks completed
    • L2 corridor partition first fix, in progress
    • Render to site mock up, completed
    • Start of west link bridge steelwork erection

    Progress throughout January 2009:

    • L3 walls and columns
    • Level 5 beams and slab started
    • Glass wall demolition completed
    • Level 4 plant room started
    • M&E first fix and drainage complete in Zone 1
    • L2 head tracks installation completed
    • Start of window frames in L3

    Progress throughout December 2008:

    • L4 walls started in L4
    • L2 head tracks installation, 95% complete
    • M&E drainage works continuing in Undercroft
    • M&E 1st fix, ongoing at L1. Works commenced on L2, Zone 1
    • Window frames installation nearly completed in L1
    • Start of window frames in L2

    Progress throughout November 2008:

    • L3 slab completed
    • L3 walls in progress
    • L4 slabs and beams in progress
    • M&E 1st fix in progress at L1
    • Temporary waterproofing at L3

    Progress throughout October 2008:

    • L2 slab, complete
    • L3 slabs completed in TC4
    • L3 walla and beams in progress
    • L4 beams and slabs started in TC4
    • Electrical cast-in conduits ongoing in cores
    • L1 head tracks installation ongoing
    • M&E started at L1
    • First delivery of window frames

    Progress throughout September 2008:

    • Drainage connection to the South loop road, completed
    • L1 slab hollowcore planks and topping completed
    • L2 slab hollowcore planks completed
    • Undercroft waterproofing, ongoing

    Progress throughout August 2008:

    • L2 slabs concreting in TC4 area, ongoing
    • L2 slabs concreting in TC1 area, started
    • L2 walls started in Tc4 area
    • Excavation for generator plant room completed and foundation raft concreting started

    Progress throughout July 2008:

    • Drainage diversions and connections of excisting under Main building substantially completed
    • L1 slab hollowcore planks and topping at final stage
    • L2 slabs concreting in TC4 area, started
    • L2 beams installation in TC1 area, started
    • Undercroft waterproofing, in progress
    • Electrical csat-in conduits ongoing
    • Workers facilities extension completed
    • Planning discussions with CBC Planning Officer for Holding Area extension 

    Progress throughout June 2008:

    • Drainage connection to the South loop road in progress
    • Main building South drainage, completed
    • Lightning protection installation and testing works ongoing
    • Undercroft walls and L1 beams, final stage
    • Undercroft circulation path, final stage
    • L1 columns start
    • Ceiling grid start
    • Exemplar rooms partitioning, completed
    • Exemplar rooms M&E first fix, completed

    Progress throughout May 2008:

    • Drainage works in the SUDS area in progress
    • Erection of TC2
    • Undercroft walls and L1 beams, ongoing
    • L1 slab and hollowcore planks and topping, started
    • Exemplar rooms partitioning, started
    • Start of atrium facade alteration
    News
    Jobs
    Tenders

    12/02/2010

    Bouygues Construction employees show remarkable generosity towards earthquake victims in Haiti

    Following the earthquake, which struck Haiti on 12 January 2010, Bouygues Construction took immediate action....

    Read More

    18/01/2010

    Next Residents Meeting...

    Please join us at our Next Residents’ Meeting

    Read More

    15/10/2009

    Macmillian Cancer Support - Coffee Morning!

    We held a coffee morning Friday 25th September to raise money for Macmillian Cancer Support... guess how much we raised!?!?!

    Read More

    03/07/2009

    40th Birthday Donation!!

    Allan Walker (who works for the NHS) recently turned 40. Rather then receive gifts for his birthday he generously asked friends and family to donate to the Essex Air Ambulance.

    Read More

    15/07/2009

    School Artwork Project

    Local students have been involved in painting wooden panels to be installed on the blue hoardings that surround the construction site. Hopefully these will be going up later this month.

    Read More

    12/05/2009

    Broomfield Hospital reaches structural completion

    Read More

    19/03/2009

    Red Nose Day 2009

    Our team on Broomfield Site Hospital decided to help raise money by having their very own cake sale.

    Read More

    19/03/2009

    March Newsletter

    Have a look at our March 2009 Newsletter. You can view the progress of our project along with some interesting facts from the Mid Essex Hospital Trust.

    Read More

    05/02/2009

    Go for the burn! Bouygues UK's new daily workout

    Read More

    16/01/2009

    January 2009 Construction News

    Take a look at our January 2009 Newsletter!

    Read More

    05/02/2009

    Dare to wear pink?

    Read More

    28/10/2008

    Next Residents Meeting

    Read More

    17/09/2008

    Open day for NHS Staff

    Read More

    08/08/2008

    Press - August 2008

    Read More

    06/06/2008

    June - News

    Read More

    12/05/2009

    Read More

    Cigarettes onlineCheap cigarettes onlineBuy cigarettes online